AGRISOVGAZ participated in the production of metal supports for high-voltage power lines as part of a project to reconstruct a substation near the village of Tabory in the Minsk region of the Republic of Belarus.
Customer: Minsk Electric Networks (branch of RUE Minskenergo) with the support of dealer AB-RETAIL LLC (Republic of Belarus).
The goal of this project is to provide reliable and uninterrupted power supply to consumers in the service area, as well as to provide electricity to 7 hectares of energy-efficient greenhouses, which are planned to be built in the future near the village of Tabory.
This modernization will include the construction of a second 110 kV overhead line, replacement of the existing transformer with higher-power equipment, and installation of a second transformer to improve the reliability of the power supply and load distribution during substation operation.
For the project, the company "AGRISOVGAZ" produced about 100 tons of lattice supports for 110 kV transmission lines.
Today, work on installing the overhead line has been completed, and the substation modernization process has begun.
Substation reconstruction: Republic of Belarus, Minsk region, Tabory village
31|07|2024